IDOT NEWSFLASH: Special Pre-Qualifications for Bidding
on 60P97 (Item 48 on September 21 Letting)
1.9 Mandatory Pre-Bid Meeting
A mandatory pre-bid meeting will be conducted to allow bidders the
opportunity to submit, for Department review, a typed list of questions, and the
Special Qualifications Submittal. The Department will review the bidders’
questions, but is under no obligation to address such questions in an addendum.
Minutes of the pre-bid meeting will not be issued to attendees. An addendum may
be issued prior to the letting to clarify contract language as necessary.
Bidders should watch the Illinois Department of Transportation web site for
bidding announcements.
The Pre-Bid Meeting will be held at 9:30AM, Thursday, August 30, 2012
Illinois Department of Transportation
201 West Center Court
Schaumburg, IL 60196-1096
The Pre-Bid Meeting attendance is mandatory for all prospective bidders.
Attendance will be taken. Please note that once the presentation begins the sign
in sheets will be copied and no late attendees will be allowed to sign in or
join the meeting. Failure on the part of a prime contractor to attend will cause
the contractor’s request for authorization to bid to be denied.
1.10 Bidders’ Special Qualifications Submittal
By the conclusion of the mandatory Pre-Bid Meeting all prospective bidders
shall provide a bidders’ Special Qualifications Submittal; information as listed
in points 1 through 11 below, as applicable to Contract article specifications
herein, which must be presented to:
Mr. Naser Gholeh, P.E., Resident Engineer
Illinois Department of Transportation
Bureau of Traffic, Electrical Maintenance Operations
If the bidder’s Special Qualifications submittal, as presented to the Engineer,
does not meet Contract 60P97 requirements as listed herein, the bidder will not
be qualified to bid on the EMC 2013-2015
Special Qualifications Submittal Items:
- Name of the bidding company and its owners and/or officers
- Resumes of the proposed:
• Project Manager
• Administration Manager
• Advanced Systems Manager
• Lighting and Extra Systems Manager
• Pump Station Manager
• Traffic Signal Manager
• Advanced Systems Specialist
• Pump Station Specialist
• SCADA Specialist
• SCADA Trainee
• Surveillance Specialist
• Traffic Signal Specialist
- Location and description, including square footage, of:
• Bidder’s Current Headquarters
• Proposed EMC Office
• Proposed EMC Dispatch Center
• Proposed Shop Facilities
- A description of the plans for service work, or in-house test facilities
which the bidder would use, to overhaul and bench test all
electromechanical, solid state, microprocessor and analog and digital
control equipment. (Section 1, Article 3.6.4)
- A 24/7 chart of the bidder’s proposed staffing for the EMC Dispatch
Center, which shows number of personnel working and on-call each day, by the
hour (Section 1, Article 3.10.4)
- A report which provides the number of vehicles in use in the bidder’s
current operations, and the number of any additional vehicles to be
purchased or leased to meet the requirements of the EMC 2013-2015. (Section
1, Article 3.15)
- A report which summarizes the number and types of
maintenance/construction equipment currently owned or leased by the bidder.
(Section 1, Article 3.16)
- A report which details the bidder’s in-house familiarity and capability
in installing and maintaining CCTV systems. (Section 1, Article 6.0)
- A report which describes the bidder’s in-house familiarity with
Allen-Bradley PLC equipment and troubleshooting of ladder logic used in the
REVLAC and RACS systems. (Section 1, Article 6.0)
- A report which describes the bidder’s in-house work on fiber optic
systems. (Section 1, Article 6.0)
- A statement signed by the bidder that:
• He/she has read the EMC 2013-2015 and accepts the methods of payment for
work as described herein
• The Special Qualification information submitted is accurate and truthful
Bidders will be furnished with a receipt which states that the Special Bidder
Qualifications submittal was received within the required time deadline. The
submitted information will be analyzed and, if requested by the Engineer, the
prospective bidder shall facilitate an inspection of its facilities and/or
equipment. The Engineer shall determine the aggregate suitability and
acceptability of the qualification information submitted. If it is determined
that the prospective bidder is qualified to perform the work then the Department
will notify the bidder through the Illinois Department of Transportation website
stating they are approved to bid on the Electrical Maintenance Contract 60P97.
|